Hub Construction

Key updates:

  • The purchase of land was finalized.
  • On September 25th 2019, the Public Advisory Council of the City of Moncton approved the few variances necessary before a building permit can be issued
  • Revised plans for the 24,000 square foot building, architectural drawings and the site plan were revealed to partners
  • The first neighbourhood information session was held September 26th, 2019
  • After a number of delays and work stoppage due to COVID-19, the foundations were poured late August 2020
Posted in Construction.